由(you)安(an)(an)徽(hui)安(an)(an)裝(zhuang)合(he)肥分(fen)公司承建(jian)的合(he)肥市濱湖醫院發熱(re)門診及感染病區應(ying)急改造工(gong)程正在爭分(fen)奪秒施工(gong),與時間賽跑。
項目主體工程為新建一棟三(san)(san)層發熱門診(zhen)樓和(he)一棟三(san)(san)層醫護樓,總(zong)建筑面積3750平(ping)方米(mi),11月7日開工進場,要(yao)求(qiu)12月7日竣工交(jiao)付(fu)醫院(yuan)方使用。
自(zi)11月(yue)初接(jie)(jie)到(dao)項(xiang)(xiang)(xiang)目(mu)(mu)任務以來(lai),面對(dui)一(yi)個月(yue)完成三層結構(gou)(gou)方(fang)艙醫院(yuan)主(zhu)體機構(gou)(gou)、內部(bu)安(an)(an)(an)(an)裝、室外(wai)裝飾的(de)(de)(de)極限工(gong)(gong)(gong)(gong)(gong)期(qi),安(an)(an)(an)(an)徽安(an)(an)(an)(an)裝公司(si)高度(du)(du)重視、精心組(zu)織、科學安(an)(an)(an)(an)排(pai)、迎難而上(shang),全(quan)力以赴加(jia)快工(gong)(gong)(gong)(gong)(gong)程(cheng)(cheng)建設(she),期(qi)間(jian),公司(si)領導(dao)多(duo)次前往項(xiang)(xiang)(xiang)目(mu)(mu)現(xian)場幫助協調(diao)解決工(gong)(gong)(gong)(gong)(gong)程(cheng)(cheng)施(shi)工(gong)(gong)(gong)(gong)(gong)中(zhong)的(de)(de)(de)難點、困(kun)難,為項(xiang)(xiang)(xiang)目(mu)(mu)人員(yuan)(yuan)鼓勁加(jia)油;公司(si)相關部(bu)門負(fu)責(ze)人駐(zhu)(zhu)扎項(xiang)(xiang)(xiang)目(mu)(mu)一(yi)線(xian),指導(dao)協調(diao)內部(bu)流(liu)程(cheng)(cheng)、現(xian)場施(shi)工(gong)(gong)(gong)(gong)(gong)、外(wai)部(bu)對(dui)接(jie)(jie)、質量安(an)(an)(an)(an)全(quan)等一(yi)應事務;分(fen)公司(si)第一(yi)時間(jian)組(zu)織精干力量進(jin)入(ru)項(xiang)(xiang)(xiang)目(mu)(mu)現(xian)場,梳(shu)理現(xian)場情況,核對(dui)圖紙清(qing)單,進(jin)行(xing)施(shi)工(gong)(gong)(gong)(gong)(gong)準(zhun)備。從公司(si)領導(dao)到(dao)項(xiang)(xiang)(xiang)目(mu)(mu)一(yi)線(xian),安(an)(an)(an)(an)徽安(an)(an)(an)(an)裝公司(si)自(zi)上(shang)而下以高度(du)(du)的(de)(de)(de)使命感(gan)和責(ze)任感(gan),投入(ru)到(dao)緊張的(de)(de)(de)工(gong)(gong)(gong)(gong)(gong)程(cheng)(cheng)建設(she)中(zhong)去(qu)。項(xiang)(xiang)(xiang)目(mu)(mu)管理人員(yuan)(yuan)披(pi)星戴月(yue),從早上(shang)到(dao)夜間(jian)駐(zhu)(zhu)守在項(xiang)(xiang)(xiang)目(mu)(mu)一(yi)線(xian),每(mei)日召(zhao)開工(gong)(gong)(gong)(gong)(gong)程(cheng)(cheng)會議(yi),討論施(shi)工(gong)(gong)(gong)(gong)(gong)工(gong)(gong)(gong)(gong)(gong)作進(jin)展(zhan)(zhan),制定下一(yi)步工(gong)(gong)(gong)(gong)(gong)作計劃,安(an)(an)(an)(an)排(pai)交叉作業工(gong)(gong)(gong)(gong)(gong)序(xu)。為保障(zhang)夜間(jian)施(shi)工(gong)(gong)(gong)(gong)(gong)安(an)(an)(an)(an)全(quan),項(xiang)(xiang)(xiang)目(mu)(mu)部(bu)安(an)(an)(an)(an)排(pai)兩名安(an)(an)(an)(an)全(quan)員(yuan)(yuan)輪流(liu)值守項(xiang)(xiang)(xiang)目(mu)(mu)現(xian)場,夜間(jian)在項(xiang)(xiang)(xiang)目(mu)(mu)現(xian)場不斷巡查確保施(shi)工(gong)(gong)(gong)(gong)(gong)安(an)(an)(an)(an)全(quan)、高效開展(zhan)(zhan)。
為搶抓(zhua)工(gong)期,項(xiang)目(mu)(mu)(mu)部迅(xun)速調集(ji)人(ren)力(li),自開工(gong)以來(lai),項(xiang)目(mu)(mu)(mu)一(yi)線施工(gong)人(ren)員一(yi)直保持在(zai)150人(ren)左右,采取24小時(shi)輪(lun)班制度,兩班倒的方(fang)式,“人(ren)歇(xie)工(gong)地(di)不(bu)(bu)停”,在(zai)嚴格實(shi)施安全防疫的同時(shi)加(jia)班加(jia)點搶時(shi)間(jian),趕任務(wu),確(que)保項(xiang)目(mu)(mu)(mu)現場(chang)施工(gong)不(bu)(bu)斷推進(jin),即使是在(zai)不(bu)(bu)利于施工(gong)作業的雨天(tian),大(da)家也合理安排施工(gong)計劃(hua),主(zhu)動(dong)放(fang)棄休息,在(zai)已經封頂的一(yi)層、二層結(jie)構中(zhong)進(jin)行(xing)水、電、通風、內部裝飾等工(gong)作,全力(li)以赴加(jia)快項(xiang)目(mu)(mu)(mu)建設進(jin)度。
截止到目(mu)前,方艙(cang)醫院項目(mu)三層樓體已拔地而(er)起,主(zhu)體結構施工和其他(ta)各項配套設施正在迅速有序(xu)推進中(zhong)。在接下來(lai)施工過程中(zhong),安徽安裝公司將用(yong)自(zi)己(ji)的使命擔當(dang)和高(gao)效(xiao)的執行力(li)展現安徽安裝速度(du),誓要打贏這(zhe)場硬(ying)仗(zhang),確保圓滿完(wan)成這(zhe)一光榮而(er)艱巨的任務(wu),為合肥市疫情(qing)防(fang)控貢(gong)獻安徽安裝力(li)量(liang)。
夜間(jian)綁扎三層地板鋼筋,雨(yu)天夜間(jian)搶工
雨天夜間搶工(gong)
二(er)層頂板結(jie)構吊裝
三層墻體輕鋼結構(gou)安裝(zhuang)
重鋼(gang)結構吊裝