近日,安徽安裝合肥(fei)分公司肥(fei)西安信立士項目(mu)(mu)(mu)(mu)順利(li)完成(cheng)了5#樓(lou)結構驗收,至此該(gai)項目(mu)(mu)(mu)(mu)5個單體項目(mu)(mu)(mu)(mu)已全部完成(cheng)了結構驗收。項目(mu)(mu)(mu)(mu)已全面進(jin)入室(shi)內粉刷(shua)及(ji)(ji)地(di)坪(ping)施(shi)(shi)(shi)工以及(ji)(ji)室(shi)外輔助生產配套項目(mu)(mu)(mu)(mu)、總圖運輸及(ji)(ji)廠(chang)區管網等施(shi)(shi)(shi)工階(jie)段,項目(mu)(mu)(mu)(mu)部目(mu)(mu)(mu)(mu)前(qian)正全力(li)(li)搶(qiang)抓有利(li)施(shi)(shi)(shi)工天氣,保持(chi)大干快上的施(shi)(shi)(shi)工熱情(qing),全力(li)(li)推進(jin)項目(mu)(mu)(mu)(mu)施(shi)(shi)(shi)工進(jin)度。
肥西安信(xin)立士項目位于(yu)合肥市(shi)肥西縣,工程造價(jia)8420萬,合同(tong)工期為390個日歷天。工程分別為1#2#生產(chan)車(che)間(jian)、3#4#研發樓、5#綜合樓以及輔助生產(chan)配套項目、總圖運輸及廠區管網(wang)(含綠化(hua))等主要施工內容,總建筑面積約4.1萬㎡。
該(gai)項(xiang)目自去年(nian)6月(yue)開工(gong)(gong)(gong)(gong)以來,前期(qi)由于(yu)受到疫情、天氣(qi)、人員(yuan)等各種(zhong)因素(su)影響,給工(gong)(gong)(gong)(gong)程施(shi)工(gong)(gong)(gong)(gong)進度和工(gong)(gong)(gong)(gong)期(qi)造成很大影響,為了(le)節(jie)約時間,保(bao)(bao)證工(gong)(gong)(gong)(gong)程的(de)順(shun)利施(shi)工(gong)(gong)(gong)(gong),高(gao)效(xiao)完(wan)成施(shi)工(gong)(gong)(gong)(gong)任務(wu),項(xiang)目部科學部署、精心組織,通(tong)過(guo)開展“強基固本保(bao)(bao)安康、提(ti)質(zhi)增效(xiao)爭一流”勞(lao)動競(jing)賽(sai)活動,采取優化施(shi)工(gong)(gong)(gong)(gong)方案、技術交底、人員(yuan)調配(pei)、安全巡查、樣板引路等多種(zhong)有(you)(you)效(xiao)方法,不(bu)斷提(ti)高(gao)工(gong)(gong)(gong)(gong)作效(xiao)率,有(you)(you)力推(tui)動了(le)施(shi)工(gong)(gong)(gong)(gong)進度,成功搶回了(le)前期(qi)耽誤的(de)時間。目前項(xiang)目在(zai)保(bao)(bao)證工(gong)(gong)(gong)(gong)程安全質(zhi)量的(de)前提(ti)下正處于(yu)大干(gan)搶工(gong)(gong)(gong)(gong)階段,5棟單體建筑施(shi)工(gong)(gong)(gong)(gong)同步進行,近期(qi)項(xiang)目工(gong)(gong)(gong)(gong)程總量已(yi)完(wan)成70%。
接下來,項(xiang)目部將按照施工(gong)(gong)部署安(an)排,對于(yu)剩余工(gong)(gong)程施工(gong)(gong)內容進行周(zhou)密的(de)(de)計劃(hua)安(an)排,按周(zhou)細(xi)化施工(gong)(gong)任(ren)務,優化施工(gong)(gong)方案,通過(guo)增加(jia)班組人(ren)員、搶(qiang)抓工(gong)(gong)作(zuo)時間、加(jia)強質(zhi)量(liang)巡查(cha)、做好工(gong)(gong)序交接等有(you)力措施保證工(gong)(gong)程的(de)(de)有(you)序推進,確(que)保在六月底順(shun)利完成總目標任(ren)務。
、
4#研(yan)發樓
5#綜合樓(lou)