只爭(zheng)朝夕謀(mou)發(fa)展,爭(zheng)分(fen)奪秒抓(zhua)落實。連日(ri)(ri)來,建(jian)工安(an)裝合肥(fei)分(fen)公司經開區臨湖智能制造產業園項(xiang)目部搶抓(zhua)施(shi)工關鍵期,緊緊圍繞既(ji)定目標任務,抓(zhua)重點、抓(zhua)突破、抓(zhua)攻堅,帶領(ling)全(quan)(quan)體參建(jian)人員夜以繼(ji)日(ri)(ri),奮力沖刺,切實推動項(xiang)目建(jian)設全(quan)(quan)面提(ti)速(su)、提(ti)檔進位。
1月6日,建工(gong)安裝合肥分(fen)公司經(jing)開區臨(lin)湖(hu)智能制造產業園項目部組織召開了“沖(chong)刺年末,全力保生產”推進會,以點(dian)(dian)對(dui)點(dian)(dian)專項研究,面(mian)對(dui)面(mian)詳(xiang)(xiang)細部署,集(ji)中力量抓重(zhong)點(dian)(dian)、破難點(dian)(dian)、創(chuang)亮點(dian)(dian)。進一(yi)步明確主攻方向,制定詳(xiang)(xiang)細的施工(gong)進度計劃及(ji)實(shi)施方案,將重(zhong)點(dian)(dian)工(gong)作劃分(fen)責任(ren)區,責任(ren)到人,為順利高效完成年前最后(hou)生產節(jie)點(dian)(dian)任(ren)務(wu)奠定堅實(shi)基礎。
組(zu)織召開“沖(chong)刺年末(mo),全力保生產”推進會
截(jie)至目前,QA一(yi)層(ceng)完(wan)成(cheng)(cheng)100%,焊裝(zhuang)車間完(wan)成(cheng)(cheng)95%,沖壓(ya)車間完(wan)成(cheng)(cheng)20%,站房完(wan)成(cheng)(cheng)90%。沖壓(ya)車間與站房管廊管道正在進行(xing)中(zhong),QA樓一(yi)層(ceng)水(shui)電風施(shi)工全部完(wan)成(cheng)(cheng),車間一(yi)閣樓組空(kong)安(an)(an)(an)裝(zhuang)18臺(tai),配電柜安(an)(an)(an)裝(zhuang)94臺(tai),橋架安(an)(an)(an)裝(zhuang)2000米,電線電纜安(an)(an)(an)裝(zhuang)12000余(yu)米,消(xiao)防(fang)(fang)報警設備安(an)(an)(an)裝(zhuang)600余(yu)套,消(xiao)防(fang)(fang)水(shui)管安(an)(an)(an)裝(zhuang)9000余(yu)米。
組合式空(kong)調與風管連(lian)接
沖壓(ya)車間高跨區域(yu)管(guan)道安裝
組合式空調管(guan)路系統樣板確認
風(feng)起,就要揚(yang)帆;乘勢(shi),定(ding)能快(kuai)上(shang)。在這個蓬勃(bo)的冬天(tian),建工安裝合肥分公司正以(yi)大項(xiang)目、好項(xiang)目為強勁支撐力,以(yi)最佳的成色(se)收官,以(yi)最好的起勢(shi)開新局,以(yi)高質(zhi)量項(xiang)目建設推動公司高質(zhi)量發展。